Laguna Niguel's City Center and Ziggurat: A Buyer's Timeline

Drive Alicia Parkway through the middle of Laguna Niguel and you pass the two largest pieces of unfinished business in south Orange County. One is the roughly 25-acre former justice center site, bounded by Pacific Island Drive, Alicia Parkway and Crown Valley Parkway, where the city approved a new downtown in July 2022. The other is William Pereira's stepped federal building, the Ziggurat, on 89 acres that changed hands this summer.

Both sites made real progress in 2026. A final tract map was recorded, a revised plan was approved and a $207 million sale closed. Even so, City Center's developer is still arranging financing ahead of a December 2, 2026 ground lease deadline that County staff have proposed extending into 2027, and the Ziggurat's new owner has not yet shared a plan with the city. A buyer comparing homes near the center of the city is pricing streets that will look much as they do now for some time, next to two sites with owners and ambitions but no construction start.

Two kinds of progress, side by side

The two properties are at very different stages, and the gap matters if you are weighing a home within a few minutes of either one.

Site Who controls it What exists on paper Next dated milestone
Laguna Niguel City Center County of Orange owns the land; Laguna Niguel Town Center Partners is the developer 110,000 sq ft retail, 15,000 sq ft office, 275 apartments, new county library Ground lease due December 2, 2026, with County staff proposing extension options to September 1, 2027
Former Chet Holifield Federal Building Laguna Ridge Health Care Development, LLC, a Hoag affiliate Existing 1-million-sq-ft building on 89 acres No redevelopment application on the city's project tracker as of November 10, 2026

City Center is a defined project waiting on financing. The Ziggurat is a defined owner whose plans have not yet gone before the city. A home near each site is exposed to a different kind of uncertainty.

City Center got smaller so it could get built

The project the city approved in 2022 included 158,000 square feet of commercial space, 77,000 of it office, plus a two-story parking structure. As the Orange County Register reported in January 2026, office space has been cut to 15,000 square feet, down 81%. Retail is set at 110,000 square feet, and the parking structure has been dropped in favor of surface parking. Bryon Ward of Burnham-Ward Properties, who leads the retail side, told the Register, "Our market has changed quite a bit," and said the changes were made "to reduce the intensity of the project in order to simplify it, reduce construction costs, and enhance the viability of the project."

The work is split between two developers under the Laguna Niguel Town Center Partners name. Burnham-Ward is designing and building the retail and the library, and Sares Regis Group is building the apartments. The apartments are planned as one- to three-bedroom units plus townhouses. The County of Orange Public Library branch is moving into the heart of the new center.

A September 2026 County staff report lists this year's progress. The developer recorded Final Tract Map No. 19024 on June 16, 2026, which created the individual legal lots and easements the project needs. The city approved the changed plan on May 28, 2026, and in June it extended the project's site development permit and use permit by 18 months, to December 21, 2027. In December 2025 the County Board approved an 89-year ground lease with total estimated payments to the County of about $452 million over the full term.

The same report also explains why the calendar has moved. The developer told the County it needs more time to secure financing, finish construction drawings and negotiate the general contractor agreement before signing the ground lease, which is currently due on or before December 2, 2026. County staff proposed two more extension options. The first runs six months to June 1, 2027, for an $80,000 payment, and the second runs three more months to September 1, 2027, for $50,000. The report says signing the lease and starting heavy demolition "may be delayed from December 2026 to September 2027." The developer maintains that the expected completion date is unchanged, because some on-site preconstruction work, including hazardous materials remediation, fencing and tree removal, will now happen during the option period.

In January, the Register reported a groundbreaking ceremony planned for summer 2026 and heavy site work at the end of the year. The September County report replaces that calendar. On publish day, the date to watch is whether the ground lease is signed by December 2 or the developer uses the 2027 options.

The Ziggurat has a new owner and a slow road ahead

The General Services Administration announced on June 30, 2026 that it had sold the former Chet Holifield Federal Building to Laguna Ridge Health Care Development, LLC, an affiliate of Hoag Memorial Hospital Presbyterian. The sale brought in more than $207 million, and GSA called it among the largest redevelopment site sales in Orange County history. Hoag CEO Robert Braithwaite said the organization is committed to "a thoughtful, long-term approach which will enable Hoag to better serve the residents and businesses of south Orange County."

The sale came after two earlier attempts. The Register's coverage of the sale recounts a 2023 auction with a preservation requirement that drew no bidders, then a 2024 auction without that requirement where bidding passed $160 million but the sale never closed. According to Preserve Orange County, the buyer chose not to execute a conservation and preservation easement. Instead it placed $2 million into a mitigation fund administered by the Orange County Community Foundation. The building's scale model and original design drawings are going to the Laguna Niguel Historical Society.

Mayor Gene Johns told the Orange County Register on the day of the sale that he imagines the site, next to Aliso & Wood Canyons Wilderness Park, won't be an all-medical facility. On timing, he pointed to the building's age, materials and history. "It will be several years, I'm sure," he said.

What is actually being built comes in small batches

In a city this built out, the sites with construction fencing up today are small. The city's major projects tracker, dated November 10, 2026, lists Cove @ El Niguel, 22 townhome-style homes at 30667 Crown Valley Parkway, as under construction. It also lists a 24-unit townhome project at 29001 Paseo de Colinas, approved by the Planning Commission in February 2025, and a 108-unit senior living center at Grace Church on La Plata Drive, approved by the City Council in May 2023. On the retail side, the tracker lists a new Shake Shack with a double-lane drive-thru at 23810 Aliso Creek Road as under construction, and a remodel of The Village shopping center at 30001 Crown Valley Parkway that adds restaurant space and outdoor seating.

Together, those three residential projects add up to 154 homes. City Center's 275 apartments alone would outnumber all three combined. Laguna Niguel's large-scale housing change is concentrated on one parcel, and that parcel's construction start now depends on a financing close. For a buyer, the pipeline outside the center of the city is modest and dated, while the one large addition will arrive on the developer's financing timeline.

Reading a home near Alicia Parkway this winter

The practical takeaway is to value the street as it is. A condo near Pacific Island Drive or a house within a short drive of Alicia Parkway should be compared against recent sales on its own merits: the floor plan, the association and the daily route. Don't add a premium for a downtown with no construction date yet. If City Center moves forward on the County's proposed schedule, heavy work could begin around September 2027. That means nearby owners should plan for a construction period before they see an open plaza.

Road work belongs on the same calendar. A March 2026 city staff report describes a planned fourth westbound lane on Crown Valley Parkway, running from the I-5 southbound off-ramp to Cabot Road, with bridge widening and new landscaping and lighting at Forbes Road. If your commute uses the north end of Crown Valley, that project is worth tracking along with the two big sites.

For the Ziggurat, the first meaningful checkpoint will be Hoag sharing its plans for the property. Until then, homes near the Alicia Parkway edge of Aliso & Wood Canyons are priced on what's there today: the wilderness park access, the existing roads and the building.

Frequently asked questions

Is Laguna Niguel City Center under construction? As of the city's November 10, 2026 tracker, City Center was listed as approved, not under construction. The September 2026 County report put ground lease signing and heavy demolition as late as September 2027, depending on extensions.

Will the Laguna Niguel library move? Yes. The plan relocates the County of Orange Public Library branch into a new building at the center of the project.

Who owns the Ziggurat now? Laguna Ridge Health Care Development, LLC, a Hoag Memorial Hospital Presbyterian affiliate, bought it from GSA in a sale announced June 30, 2026.

If you own near Alicia Parkway and want to know what your home is worth on today's street, not on a downtown that's still in financing, Active Realty, Inc. and the Justin Tye Real Estate Group will price it against the sales that matter. Start with a free home valuation, or book a time to go through the City Center and Ziggurat calendar as it applies to your address.

Work With Us

We combine expertise, technology, and dedication to deliver exceptional results. Whether you're buying or selling, our team is here to guide you every step of the way. Let us help you find the perfect home!

Follow Us on Instagram